Project Update 23


Production & Construction, Chapter 2

The project’s average daily production in 2007 was 144 thousand barrels, shipped to market in 56 tanker shipments. The project has so far produced nearly 242 million barrels of crude oil.

Project oil facilities, located about 400 kilometers south of N’Djamena, were not affected by an episode of civil unrest in the capital of Chad.