Project Update 25


Production & Construction, Chapter 2

The project to date has sent over 288 million barrels of crude oil to the world market.

A total of 60 new oil wells were drilled and brought on line in the last year and the drilling program will add as many as 100 new wells in 2009.

A planned second phase high pressure water injection project was launched to maintain oilfield pressure and thus support crude oil output.