Table of Contents and Snapshot
Summary (PDF)
Chapter 2 - Construction
Progress (PDF)
The Project anticipates that it will begin producing oil from one of the three
oilfields in southern Chad in mid-2003. At the close of 2002, the Project -
including engineering, procurement, and construction - was well over 75%
complete.
- Almost all of the export pipeline had been welded and buried in its trench.
- Thirty-eight production oil wells have been drilled and tests of these first
wells have been meeting expectations.
- Refurbishment of the Floating Storage and Offloading vessel and fabrication
of its mooring was nearing completion in Asia.
- Facilities construction in the Oilfield Development Area accelerated in
December after resolution of a multi-week job action by truckers, which made
it possible to clear a backlog of freight essential to the construction effort.
Chapter 3 - Reportable EMP
Situations (PDF)
Field monitors recorded 25 Project-reportable Environmental Management Plan
non-compliance situations this quarter, the second lowest quarterly level in
two years.
- One minor Project reportable spill took place on land this quarter. There
were no spills into water or wetland areas.
- No critical (Level III) non-compliance situations have been recorded by the
Project to date.
Chapter 4 - Safety (PDF)
No Project-recordable lost time incidents occurred in the fourth quarter of
2002 and the overall worker safety record at Project work sites continues to
be very good.
- The traffic accident injury rate for the Project is 59 per 100 million miles
driven, compared to the North American rate of 116 per 100 million miles
driven.
- Workers for facilities construction contractor TCC have topped the 21
million hour mark without a lost time incident.
- The oil well drilling operation, including contractors Pride Forasol and
Schlumberger, was nearing five million worker hours without a lost time
incident.
Chapter 5 - Consultation &
Communication (PDF)
Public consultation increased in the fourth quarter to 680 sessions, reaching
more than 23,000 people.
- Support for pipeline construction activities in southern Chad contributed to
the rise in consultation levels.
- The Project consulted with fishermen in the Kribi area in preparation for
the start of offshore construction in the first quarter of 2003.
- Consultation meetings on the Project's Area Specific Oil Spill Response
Plans began in November in Chad. Similar meetings will occur in Cameroon in
January 2003.
The Project launched an improved dust control program in Chad.
- A fleet of 28 road watering trucks was assigned to dust control duty in
southern Chad along the Project-upgraded road and in the Oilfield Development
Area.
- Several sections of road in the Oilfield Development Area will be treated
with DBST, a type of paving material. Other dust control measures will also be
evaluated.
Chapter 6 - Compensation
(PDF)
The Project paid nearly 519 million FCFA ($798 thousand) in cash and in-kind
compensation to individual land users in the fourth quarter of 2002.
- In Chad, individual compensation distributed in the fourth quarter totaled
215 million FCFA ($330 thousand).
- In Cameroon, individual compensation paid in the fourth quarter was nearly
304 million FCFA ($467 thousand).
- Since the compensation program began, approximately 6.75 billion FCFA ($10.4
million) in cash and in-kind payments has been distributed to individual land
users.
The Project's regional and community compensation programs made good progress
in the fourth quarter.
- In Cameroon, implementation of the program began after a nearly year-long
consultation effort to help communities choose their micro-development
projects.
- In Chad, consultations are well along in all of the communities eligible for
the program and nearly all of them have submitted proposals for projects.
Chapter 7 - EMP Monitoring &
Management Program (PDF)
In December, a cooking fire spread out of control and destroyed much of the
Komé Atan settlement, located across the road from the Komé Base Camp.
- Project fire fighters responded to the fire and rendered assistance. The
fire caused no serious injuries, although one burn victim was treated at a
Project camp clinic.
- The Project supported the government's relief efforts through donations of
wood and clothing, and by laying out new streets, among other measures.
- The fire struck as the Project was completing a set of action steps to
improve certain conditions in the settlement.
Chapter 8 - Local Employment
(PDF)
For the first time since construction began, the size of the Project's direct
workforce has started to fall.
- The Project's overall peak workforce was reached in November with a total of
13,156 workers but then fell back to the previous quarter's level in December.
- Chadians and Cameroonians make up about three-fourths of the Project's
workforce, and about 60% of them hold skilled or semi-skilled jobs.
Wages paid to Chadian and Cameroonian workers in the fourth quarter of 2002
totaled almost 7.8 billion FCFA ($12 million).
- Wage payments to Chadian workers approached 4.1 billion FCFA ($6.3 million).
- Wage payments to Cameroonian workers were 3.7 billion FCFA ($5.7 million).
Chapter 9 - Local Business
Development (PDF)
Figures show that Project construction has driven the pace of economic growth
in Chad sharply upward (as measured by Gross Domestic Product).
- From 1999 to 2002, annual Gross Domestic Product growth has gone from only
1% to almost 11%.
- This rise tracks closely with the Project's purchasing of goods and services
in Chad, which has gone from $10 million in 2000 to $173 million over the same
time period.
- Since construction began, the Project has purchased over 151 billion FCFA
($232 million) of local goods and services from Chadian businesses.
The Project spent 59 billion FCFA ($90 million) buying goods and services from
Chadian and Cameroonian suppliers during the fourth quarter.
Chapter 10 - Training
(PDF)
Training of Chadian and Cameroonian workers during the fourth quarter totaled
1800 sessions, with class attendance of over 12,000.
Chapter 11 - Archaeology &
Cultural Resources (PDF)
Archaeological investigations in Chad and Cameroon began to shift from the
field to the laboratory this quarter as excavation at Project work sites
neared completion.
- The Cameroon team moved its collected samples into a new laboratory facility
in Douala.
- In Chad, the Project signed a contract with the University of N'Djaména to
create a new archaeology laboratory. This building is under construction.
Chapter 12 - Worker Health
(PDF)
Chapter 13 - Community Health
(PDF)
Project clinics provided 23,410 worker medical consultations during the fourth
quarter of 2002.
- The control of malaria continued as the major focus of the Project's worker
health program.
- A major dining hall upgrade was completed at the Project's Komé Base Camp,
adding a new restaurant to enhance capacity and food safety.
- A new larger Project worker clinic was opened at the central oilfield
facility to serve the construction workforce.
The initial phase of the Roll Back Malaria program in Chad has been completed.
In 2002, the two NGOs contracted by the Project to implement much of the
program distributed 37,000 bed nets in 141 Project-area villages, and provided
malaria prevention education to 122,000 people.
A year long, multi-village STDs/HIV/AIDS prevention and education program was
completed in Cameroon.
Chapter 14 - Waste Management
(PDF)
The Project reduced its hazardous waste backlog by approximately half this
quarter, primarily due to the success of a recycling program for used motor
oil in Cameroon. Over 40% of the Project's non-hazardous waste was recycled to
villages or sent to approved recycling facilities.
- The permanent waste storage facilities at the two Cameroon pump stations and
the Pressure Reducing Station were completed.
- Construction began on the permanent Komé waste management facility, which
will include hazardous and non-hazardous solid waste landfills, a hazardous
waste-capable incinerator, two domestic waste incinerators, and a waste
storage building.
- The hazardous solid waste landfill at Pump Station 3 near Bélabo has been
excavated and the liner installed. The landfill will go into operation in 2003.
Chapter 15 - Water Quality
Monitoring (PDF)
Data from two years of Project water monitoring shows that the water resources
used by the local population in the immediate vicinities of Project work sites
and water withdrawal points have not been adversely affected.
Chapter 16 - Environmental
Foundation (PDF)
Chapter 17 - Transition to Oil
Production Phase (PDF)
The Management Board of the Foundation for Environment and Development in
Cameroon (FEDEC) met in December. After reviewing progress to date, the Board
adopted a future action plan and strategic vision.
As construction moved towards the first oil production milestone in mid-2003,
work continued to build the Project's operations phase organization.
- A total of 177 Chadians and Cameroonians have been hired so far as permanent
Project technical, managerial and professional staff.
- Over 70 of the nearly 100 new technicians are working in Canada, the United
States and other countries to gain job experience.
- A training program was been developed to prepare the expatriate staff who
will mobilize to Chad and Cameroon beginning in March 2003.
Download Full Report
(PDF)
|